Shop Control
Shop control is designed to work in conjunction with a master schedule where jobs and POs reflect aggregate demand and supply dates are coordinated with dem...
Fri, 22 Sep, 2017 at 8:47 AM
When a job is initially generated, it is given a status of New and a planned start and finish date derived from its parent item’s Lead Days and Job Days set...
Fri, 22 Sep, 2017 at 8:48 AM
Job release is a mandatory process. It determines which jobs can be released to live production based on material availability. If the job release date di...
Fri, 22 Sep, 2017 at 8:49 AM
When you use MRP for job generation, it is highly unlikely that multi-level subassembly jobs will be scheduled to start on the same day. This phenomenon ty...
Fri, 22 Sep, 2017 at 8:51 AM
Job release is not a once a day process. If you have a relatively high volume of multi-level jobs, jobs should be released periodically throughout the day ...
Fri, 22 Sep, 2017 at 8:52 AM
DBA is designed for timely updating of material and labor through the Work Center Schedule screen. It is time consuming and inefficient to manage work...
Fri, 22 Sep, 2017 at 8:53 AM
Real time material and labor updating through the Work Center Schedule screen is not only practical, it saves a great deal of time and dramatically improves...
Fri, 22 Sep, 2017 at 8:55 AM
A manual override to the job priority calculation is not provided nor is it needed. A manual override encourages expediting, which is a destructive practice...
Fri, 22 Sep, 2017 at 8:56 AM
Does the system track whether or not a Traveler has been printed yet? The software does not track whether or not a Traveler has been printed. Our recom...
Mon, 9 Oct, 2017 at 10:30 AM
How to reverse an issue of a component whose characteristic structure was altered When a stock item has had a change in characteristic structure, such a...
Mon, 9 Oct, 2017 at 10:35 AM