Job Schedule - How can I change the Required Date for a 'To Stock' Job?
For a 'To Stock', manually created, Job the Required Date will be set equal to the Finish Date. After Job creation, the Required Date cannot be manually changed, but it will move inward if there is demand (within the item's planning period) that drops projected supply below zero. It will not move outward.